1. Site Inspection for 15 kW PV solar system
2. Conduct Energy audit
3. Utility approval and permit application
4. ESA - Electrical Safety Authority pre-inspection
5. Design system and produce the electrical drawings
6. Install the racking system and the PV panels
7. Install the inverter
8. Make the necessary connections to the main panel
9. ESA - Electrical Safety Authority post-inspection
10. Final Energy Audit Inspection
Products to be installed
- Thornova - TS-BG72 550W Bifacial Solar Panels (15 kW)
- Fronius - Primo 15.0-1 208/240 Full 15.0 kW, 1ph, DC Disco -Com Incl. (10 kW)
- PV Panel Racking (Various items for the racking system, including all clamps, railings and wire)