1. Site Inspection for 10 kW PV solar system
2. Conduct Energy audit
3. Utility approval and permit application
4. ESA - Electrical Safety Authority pre-inspection
5. Design system and produce the electrical drawings
6. Install the racking system and the PV panels
7. Install the inverter
8. Make the necessary connections to the main panel
9. ESA - Electrical Safety Authority post-inspection
10. Final Energy Audit Inspection
Products to be installed
- Longi - LR5-72HPH-550M Mono (PV Panels 550W)
- Growatt - MIN 7600TL-XH-US, 3MPPT, Hybrid, 600V cETLus, UL1741SB, UL9540, Sunspec RSD, WIFI/ETH (Hybrid - Inverter)
- Tigo - TS4-A-O Optimizer max 1000Vdc UL, 1.2m cable, MC4, (Optimizers)
- PV Panel Racking (Various items for the racking system, including all clamps, railings and wire)